Construction payment claims in New South Wales

For supported NSW construction matters, organise a payment claim under the Building and Construction Industry Security of Payment Act 1999.

What is different in NSW?

Current and legacy pathways coexist. Contracts made before 21 October 2019 may remain under older reference-date rules, so the contract date matters. A claim must identify the work or related goods and services, state the amount claimed and say that it is made under the Act. Residential matters require Home Building Act checks. A head contractor claiming from a principal may also need the approved supporting statement. Service is its own step: an email address is suitable only where it was specified for service of that kind.