Builder won't pay? The 5-step playbook for subcontractors

You don't have to wait months or go to court. Every state has Security of Payment laws built for exactly this.

  1. Send a proper payment claim, not just an invoice: required content, the statement, and the right address.
  2. Diary the payment schedule deadline: 10 business days in NSW and VIC, 15 in QLD.
  3. No schedule? They owe the lot. You can recover it as a debt or go to adjudication.
  4. Not paid by the due date? Give written notice of your intention to suspend work.
  5. Apply for adjudication within the strict deadline, through an authorised nominating authority.

Deadlines by state

NSWVICQLD
Payment schedule10 BD10 BD15 BD
Max payment term (subbie)20 BD20 BD25 BD
Adjudication after disputed schedule10 BD10 BD30 BD
Christmas shutdown (not business days)27–31 Dec22 Dec – 10 Jan27–31 Dec

BD = business days. Confirm against the Act and your contract.

Owed money on a job right now?

Work out every deadline free, then build a valid payment claim and the full recovery pack (reminders, suspension notice, adjudication submissions) in about 15 minutes.

Make a payment claim Free deadline calculator

More: How to make a payment claim in NSW · Victoria's 2026 Security of Payment reforms: what changed for payment claims · How to make a payment claim in Queensland (BIF Act) · Payment schedule deadline calculator · Suspending work for non-payment: the notice · Applying for adjudication: a subcontractor's guide · Payment claim template: what a valid claim needs